Preparation of Claim Assessment Report – Rehabilitation of CHA Estates Phase III – Contract WW127X

Client: Wastewater Management Authority
Contractor: Sotravic Ltée
Contract Value: MUR 151 million

 

Dispute declared by contractor based on the FIDIC IV Conditions of Contract, in respect of:

  • Contract Authority’s failure to give Possession of Site on Vallée Pitot Estate.
  • Contracting Authority’s failure to give Possession of Site la Caverne Estate
  • Additional costs Offsite Costs due to Delays
  • Increase in basic labour, materials & equipment costs after original completion date (Vallée Pitot and La Caverne Estates)
  • Delay in Provision of Diversion to Existing Services at Pointe Aux Sables Estate
  • Unaccounted detailed Survey and Removal of Debris
  • Employer’s failure to give possession of site and constraining condition during Outfall Sewer construction
  • Administrative order preventing provision of plastic inspection chambers