Conciliation Procedures on Contract C9524 – Pipelaying Works for Residential Project – Year 2000

Client: Central Water Authority
Contractor: Gamma-Civic Ltd
Contract Value: MUR 15 million

 

Dispute declared by contractor based on provisions of Clause 67 of the FIDIC IV Conditions of Contract

 

Claim based on:

  • Re-alignment of part of off-site water feeding main into water-logged ground
  • Delay in granting of possession of site
  • Extension of time, with associated costs

 

Amount of claim: MUR 4.0 million